PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 7838
CONTRACT: Dean Ave, Allis Ave, Tyler Cir & Seth Cir
Percentage of Contract Completed:
98.57%
|
Associated Projects:
- Dean Ave, Allis Ave, Tyler Cir & Seth Cir (11432)
|
| PROJECT: |
Dean Ave, Allis Ave, Tyler Cir & Seth Cir |
| Project Number: |
11432 |
| Bid Due Date: |
04/29/21
|
| Bid Open Date: |
04/29/2021 |
| Estimated Start Date: |
06/14/2021
|
| Estimated Completion Date: |
11/04/2021
|
| Percent of Project Completed: |
98.57 %
|
| Contract Amount: |
$3,741,604.39
|
| Project Contractor: |
SPEEDWAY SAND & GRAVEL INC
|
| Construction Year: |
2021 |
| Construction Type: |
Street |
| District: |
15,
|
|
PROJECT CONTACT: |
| Project Manager: |
Jim Wolfe |
| Phone: |
608-266-4099 |
| Email: |
jwolfe@cityofmadison.com |
| Inspector: |
Belohlavek, Rachel |
| Phone: |
608-7836 |
Documents & Specs
|