CONTRACT NUMBER: 7843
CONTRACT: Ronald Reagan Ave, John Wall Dr and Merchant St
Percentage of Contract Completed:
97.7%
|
Associated Projects:
- Ronald Reagan Ave, John Wall Dr and Merchant St (11461)
|
PROJECT: |
Ronald Reagan Ave, John Wall Dr and Merchant St |
Project Number: |
11461 |
Bid Due Date: |
02/08/18
|
Bid Open Date: |
02/08/2018 |
Estimated Start Date: |
04/02/2018
|
Estimated Completion Date: |
08/10/2018
|
Percent of Project Completed: |
97.7 %
|
Contract Amount: |
$2,812,630.07
|
Project Contractor: |
Parisi Construction Co., Inc.
|
Construction Year: |
2018 |
Construction Type: |
Street |
District: |
17,
|
PROJECT CONTACT: |
Project Manager: |
Andy Zwieg |
Phone: |
608-266-9219 |
Email: |
azwieg@cityofmadison.com |
Inspector: |
Lauby, Paul |
Phone: |
|