CONTRACT NUMBER: 7850
CONTRACT: Yuma Drive Resurfacing with Utilities
Percentage of Contract Completed:
98.7%
|
Associated Projects:
- Yuma Drive Resurfacing with Utilities (11435)
|
PROJECT: |
Yuma Drive Resurfacing with Utilities |
Project Number: |
11435 |
Bid Due Date: |
04/21/17
|
Bid Open Date: |
04/21/2017 |
Estimated Start Date: |
08/14/2017
|
Estimated Completion Date: |
11/02/2017
|
Percent of Project Completed: |
98.7 %
|
Contract Amount: |
$1,571,817.44
|
Project Contractor: |
S & L Underground, Inc.
|
Construction Year: |
2017 |
Construction Type: |
Street |
District: |
10,
|
PROJECT CONTACT: |
Project Manager: |
Steve Sonntag |
Phone: |
608-267-1997 |
Email: |
ssonntag@cityofmadison.com |
Inspector: |
Mael, Stewart |
Phone: |
261-9695 |