PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 7877
CONTRACT: Warner Boat Launch Breakwater Reconstruction
Percentage of Contract Completed:
98.8%
|
Associated Projects:
- Warner Boat Launch Breakwater Reconstruction (10990)
|
PROJECT: |
Warner Boat Launch Breakwater Reconstruction |
Project Number: |
10990 |
Bid Due Date: |
01/27/17
|
Bid Open Date: |
01/27/2017 |
Estimated Start Date: |
03/15/2017
|
Estimated Completion Date: |
05/19/2017
|
Percent of Project Completed: |
98.8 %
|
Contract Amount: |
$656,186.00
|
Project Contractor: |
DRAX INC
|
Construction Year: |
2016 |
Construction Type: |
Storm |
District: |
12,
|
PROJECT CONTACT: |
Project Manager: |
|
Phone: |
|
Email: |
|
Inspector: |
Lauby, Paul |
Phone: |
|
Documents & Specs
|