PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 7901
CONTRACT: Demetral Park Path Phase 2
Percentage of Contract Completed:
81.18%
|
Associated Projects:
- Demetral Park Path Phase 2 (11515)
|
PROJECT: |
Demetral Park Path Phase 2 |
Project Number: |
11515 |
Bid Due Date: |
07/08/21
|
Bid Open Date: |
07/08/2021 |
Estimated Start Date: |
09/07/2021
|
Estimated Completion Date: |
10/21/2021
|
Percent of Project Completed: |
81.18 %
|
Contract Amount: |
$397,518.32
|
Project Contractor: |
SPEEDWAY SAND & GRAVEL INC
|
Construction Year: |
2021 |
Construction Type: |
Bike Path |
District: |
12,
|
PROJECT CONTACT: |
Project Manager: |
Aaron Canton |
Phone: |
(608) 242-4763 |
Email: |
acanton@cityofmadison.com |
Inspector: |
Lauby, Paul |
Phone: |
|
Documents & Specs
|