PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 7979
CONTRACT: Monona Bay Shoreline Repairs
Percentage of Contract Completed:
100.0%
|
Associated Projects:
- Monona Bay Shoreline Repairs (10991)
|
| PROJECT: |
Monona Bay Shoreline Repairs |
| Project Number: |
10991 |
| Bid Due Date: |
07/21/17
|
| Bid Open Date: |
07/21/2017 |
| Estimated Start Date: |
10/17/2017
|
| Estimated Completion Date: |
11/30/2017
|
| Percent of Project Completed: |
100.0 %
|
| Contract Amount: |
$94,394.00
|
| Project Contractor: |
SPEEDWAY SAND & GRAVEL INC
|
| Construction Year: |
2017 |
| Construction Type: |
Storm |
| District: |
13,
|
|
PROJECT CONTACT: |
| Project Manager: |
Sally Swenson |
| Phone: |
608-266-4862 |
| Email: |
sswenson@cityofmadison.com |
| Inspector: |
Ziegler-Henderson, Lauri |
| Phone: |
261-5585 |
Documents & Specs
|