PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 8032
CONTRACT: Olin Transfer Station Stormwater Improvement
Percentage of Contract Completed:
99.1%
|
Associated Projects:
- OLIN TRANSFER STATION STORMWATER IMPROVEMENT (53W1787)
|
PROJECT: |
OLIN TRANSFER STATION STORMWATER IMPROVEMENT |
Project Number: |
53W1787 |
Bid Due Date: |
08/18/17
|
Bid Open Date: |
08/18/2017 |
Estimated Start Date: |
10/09/2017
|
Estimated Completion Date: |
11/03/2017
|
Percent of Project Completed: |
99.1 %
|
Contract Amount: |
$234,660.50
|
Project Contractor: |
SPEEDWAY SAND & GRAVEL INC
|
Construction Year: |
2017 |
Construction Type: |
Storm |
District: |
14,
|
PROJECT CONTACT: |
Project Manager: |
Lauren Striegl |
Phone: |
608-266-4094 |
Email: |
lstriegl@cityofmadison.com |
Inspector: |
Ziegler-Henderson, Lauri |
Phone: |
261-5585 |
Documents & Specs
|