CONTRACT: Annual Construction and Reconstruction of Concrete Sidewalk and Incidental Concrete Curb & Gutter Work Ordered (District 16) By the Common Council
Percentage of Contract Completed: 86.5%
Associated Projects:
  • Sidewalk Program 2018, Ald. District 16 (11770)
PROJECT: Sidewalk Program 2018, Ald. District 16
Project Number: 11770
Bid Due Date: 03/15/18
Bid Open Date: 03/15/2018
Estimated Start Date: 05/01/2018
Estimated Completion Date: 07/31/2018
Percent of Project Completed: 86.5 %
Contract Amount: $1,315,507.00
Project Contractor: Raymond P. Cattell Inc.
Construction Year: 2018
Construction Type: Sidewalk
District: 16,
PROJECT CONTACT:
Project Manager: Bill McGlynn
Phone: 608- 266-4537
Email: wmcglynn@cityofmadison.com
Inspector: Lunde, Matt
Phone: 608-266-4088