CONTRACT NUMBER: 8093
CONTRACT: Chip Sealing 2018-East (ald dist 15, 17 &18)
Percentage of Contract Completed:
99.8%
|
Associated Projects:
- Pavement Crack Repair and Chip Seal 2018 (11784)
|
| PROJECT: |
Pavement Crack Repair and Chip Seal 2018 |
| Project Number: |
11784 |
| Bid Due Date: |
04/12/18
|
| Bid Open Date: |
04/12/2018 |
| Estimated Start Date: |
05/29/2018
|
| Estimated Completion Date: |
Not Available
|
| Percent of Project Completed: |
99.8 %
|
| Contract Amount: |
$1,111,337.16
|
| Project Contractor: |
Fahrner Asphalt Sealers, LLC
|
| Construction Year: |
2018 |
| Construction Type: |
Street |
| District: |
11,
15,
17,
18,
19,
|
|
PROJECT CONTACT: |
| Project Manager: |
Steve Sonntag |
| Phone: |
608-267-1997 |
| Email: |
ssonntag@cityofmadison.com |
| Inspector: |
Not Available |
| Phone: |
Not Available |