|
PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 8094
CONTRACT: Repairing & Sealing Pavement Cracks, Local Streets - 2018
Percentage of Contract Completed:
89.8%
|
Associated Projects:
- Pavement Crack Repair and Chip Seal 2018 (11784)
|
PROJECT: |
Pavement Crack Repair and Chip Seal 2018 |
Project Number: |
11784 |
Bid Due Date: |
04/12/18
|
Bid Open Date: |
04/12/2018 |
Estimated Start Date: |
05/29/2018
|
Estimated Completion Date: |
Not Available
|
Percent of Project Completed: |
89.8 %
|
Contract Amount: |
$65,203.00
|
Project Contractor: |
Fahrner Asphalt Sealers, LLC
|
Construction Year: |
2018 |
Construction Type: |
Street |
District: |
11,
15,
17,
18,
19,
|
PROJECT CONTACT: |
Project Manager: |
Steve Sonntag |
Phone: |
608-267-1997 |
Email: |
ssonntag@cityofmadison.com |
Inspector: |
Not Available |
Phone: |
Not Available |
Documents & Specs
|