PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 8101
CONTRACT: Wingra Creek Pedestrian Bridge Replacement
Percentage of Contract Completed:
98.8%
|
Associated Projects:
- Wingra Creek Pedestrian Bridge Replacement (11294)
|
| PROJECT: |
Wingra Creek Pedestrian Bridge Replacement |
| Project Number: |
11294 |
| Bid Due Date: |
02/08/18
|
| Bid Open Date: |
02/08/2018 |
| Estimated Start Date: |
06/25/2018
|
| Estimated Completion Date: |
06/29/2018
|
| Percent of Project Completed: |
98.8 %
|
| Contract Amount: |
$148,934.00
|
| Project Contractor: |
Drax Inc.
|
| Construction Year: |
2018 |
| Construction Type: |
Bridge |
| District: |
13,
14,
|
|
PROJECT CONTACT: |
| Project Manager: |
Lisa Coleman |
| Phone: |
608-266-4093 |
| Email: |
lcoleman@cityofmadison.com |
| Inspector: |
Hoel, Eric |
| Phone: |
|
Documents & Specs
|