PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 8108
CONTRACT: Schenk St and Richard St Resurfacing w/Utilities
Percentage of Contract Completed:
98.70%
|
Associated Projects:
- Schenk St and Richard St Resurfacing w/Utilities (11745)
|
PROJECT: |
Schenk St and Richard St Resurfacing w/Utilities |
Project Number: |
11745 |
Bid Due Date: |
03/22/18
|
Bid Open Date: |
03/22/2018 |
Estimated Start Date: |
05/25/2001
|
Estimated Completion Date: |
10/31/2018
|
Percent of Project Completed: |
98.70 %
|
Contract Amount: |
$3,526,939.33
|
Project Contractor: |
RG HUSTON COMPANY INC
|
Construction Year: |
2018 |
Construction Type: |
Street |
District: |
15,
|
PROJECT CONTACT: |
Project Manager: |
Steve Sonntag |
Phone: |
608-267-1997 |
Email: |
ssonntag@cityofmadison.com |
Inspector: |
Hoel, Eric |
Phone: |
|
Documents & Specs
|