PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 8111
CONTRACT: Utilities with Resurfacing 2018
Percentage of Contract Completed:
97.80%
|
Associated Projects:
- Utilities with Resurfacing 2018 (11654)
|
PROJECT: |
Utilities with Resurfacing 2018 |
Project Number: |
11654 |
Bid Due Date: |
04/05/18
|
Bid Open Date: |
04/05/2018 |
Estimated Start Date: |
06/14/2018
|
Estimated Completion Date: |
09/22/2018
|
Percent of Project Completed: |
97.80 %
|
Contract Amount: |
$1,949,949.10
|
Project Contractor: |
Parisi Construction Co., Inc.
|
Construction Year: |
2018 |
Construction Type: |
Street |
District: |
12,
|
PROJECT CONTACT: |
Project Manager: |
Steve Sonntag |
Phone: |
608-267-1997 |
Email: |
ssonntag@cityofmadison.com |
Inspector: |
Lauby, Paul |
Phone: |
|
Documents & Specs
|