PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 8124
CONTRACT: Darwin Rd Resurfacing w/Utilities
Percentage of Contract Completed:
92.84%
|
Associated Projects:
- Darwin Rd Resurfacing w/Utilities (11746)
|
PROJECT: |
Darwin Rd Resurfacing w/Utilities |
Project Number: |
11746 |
Bid Due Date: |
12/20/18
|
Bid Open Date: |
12/20/2018 |
Estimated Start Date: |
04/24/2019
|
Estimated Completion Date: |
06/26/2019
|
Percent of Project Completed: |
92.84 %
|
Contract Amount: |
$667,065.40
|
Project Contractor: |
Parisi Construction Co., Inc.
|
Construction Year: |
2019 |
Construction Type: |
Street |
District: |
12,
|
PROJECT CONTACT: |
Project Manager: |
Steve Sonntag |
Phone: |
608-267-1997 |
Email: |
ssonntag@cityofmadison.com |
Inspector: |
Lauby, Paul |
Phone: |
|
Documents & Specs
|