CONTRACT NUMBER: 8152
CONTRACT: Summit Maintenance Facility-Building Improvements
Percentage of Contract Completed: 100.0%
Associated Projects:
  • Summit Maintenance Facility - Building Improvements (11653)
PROJECT: Summit Maintenance Facility - Building Improvements
Project Number: 11653
Bid Due Date: 02/22/18
Bid Open Date: 02/22/2018
Estimated Start Date: 04/30/2018
Estimated Completion Date: Not Available
Percent of Project Completed: 100.0 %
Contract Amount: $275,458.00
Project Contractor: Forward Construction Group, LLC
Construction Year: 2017
Construction Type: Facilities
District: 10,
PROJECT CONTACT:
Project Manager: Paul Stauffer
Phone: 608-266-4366
Email: pstauffer@cityofmadison.com
Inspector: Not Available
Phone: Not Available