PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 8276
CONTRACT: Darbo Dr Canoe Launch 2019
Percentage of Contract Completed:
100.0%
|
Associated Projects:
- DARBO DR CANOE LAUNCH 2019 (11761)
|
PROJECT: |
DARBO DR CANOE LAUNCH 2019 |
Project Number: |
11761 |
Bid Due Date: |
04/25/19
|
Bid Open Date: |
04/25/2019 |
Estimated Start Date: |
08/15/2019
|
Estimated Completion Date: |
09/13/2019
|
Percent of Project Completed: |
100.0 %
|
Contract Amount: |
$36,815.00
|
Project Contractor: |
GREENER VALLEY LANDSCAPING
|
Construction Year: |
2019 |
Construction Type: |
Storm |
District: |
06,
|
PROJECT CONTACT: |
Project Manager: |
JoJo O'Brien |
Phone: |
(608)266-9721 |
Email: |
JOBrien@cityofmadison.com |
Inspector: |
Lauby, Paul |
Phone: |
|
Documents & Specs
|