PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 8366
CONTRACT: Sidewalk Program 2019, Ald. District 1 & 7
Percentage of Contract Completed:
95.45%
|
Associated Projects:
- Sidewalk Program 2019, Ald. District 1 & 7 (11879)
|
| PROJECT: |
Sidewalk Program 2019, Ald. District 1 & 7 |
| Project Number: |
11879 |
| Bid Due Date: |
03/07/19
|
| Bid Open Date: |
03/07/2019 |
| Estimated Start Date: |
05/13/2019
|
| Estimated Completion Date: |
Not Available
|
| Percent of Project Completed: |
95.45 %
|
| Contract Amount: |
$564,877.00
|
| Project Contractor: |
JW SCHULTZ CONSTRUCTION CO INC
|
| Construction Year: |
2019 |
| Construction Type: |
Sidewalk |
| District: |
01,
07,
|
|
PROJECT CONTACT: |
| Project Manager: |
Bill McGlynn |
| Phone: |
608- 266-4537 |
| Email: |
wmcglynn@cityofmadison.com |
| Inspector: |
Not Available |
| Phone: |
Not Available |