PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 8367
CONTRACT: Sidewalk Program 2019, Ald. District 9
Percentage of Contract Completed:
89.51%
|
Associated Projects:
- Sidewalk Program 2019, Ald. District 9 (11880)
|
PROJECT: |
Sidewalk Program 2019, Ald. District 9 |
Project Number: |
11880 |
Bid Due Date: |
02/21/19
|
Bid Open Date: |
02/21/2019 |
Estimated Start Date: |
04/15/2019
|
Estimated Completion Date: |
Not Available
|
Percent of Project Completed: |
89.51 %
|
Contract Amount: |
$863,993.00
|
Project Contractor: |
CPR INC.
|
Construction Year: |
2019 |
Construction Type: |
Sidewalk |
District: |
09,
|
PROJECT CONTACT: |
Project Manager: |
Bill McGlynn |
Phone: |
608- 266-4537 |
Email: |
wmcglynn@cityofmadison.com |
Inspector: |
Not Available |
Phone: |
Not Available |
Documents & Specs
|