PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 8502
CONTRACT: Packers Avenue Resurfacing w/Utilities
Percentage of Contract Completed:
89.11%
|
Associated Projects:
- Packers Avenue Resurfacing w/Utilities (12564)
|
PROJECT: |
Packers Avenue Resurfacing w/Utilities |
Project Number: |
12564 |
Bid Due Date: |
03/19/20
|
Bid Open Date: |
03/19/2020 |
Estimated Start Date: |
05/04/2020
|
Estimated Completion Date: |
07/10/2020
|
Percent of Project Completed: |
89.11 %
|
Contract Amount: |
$936,622.85
|
Project Contractor: |
S & L Underground, Inc.
|
Construction Year: |
2020 |
Construction Type: |
Street |
District: |
12,
|
PROJECT CONTACT: |
Project Manager: |
Steve Sonntag |
Phone: |
608-267-1997 |
Email: |
ssonntag@cityofmadison.com |
Inspector: |
Armstrong, Steve |
Phone: |
266-4914 |
Documents & Specs
|