PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 8507
CONTRACT: Crack repair: local
Percentage of Contract Completed:
94.70%
|
Associated Projects:
- Pavement Crack Repair and Chip Seal 2020 (12690)
|
| PROJECT: |
Pavement Crack Repair and Chip Seal 2020 |
| Project Number: |
12690 |
| Bid Due Date: |
03/19/20
|
| Bid Open Date: |
03/19/2020 |
| Estimated Start Date: |
04/27/2020
|
| Estimated Completion Date: |
Not Available
|
| Percent of Project Completed: |
94.70 %
|
| Contract Amount: |
$260,168.00
|
| Project Contractor: |
Fahrner Asphalt Sealers, LLC
|
| Construction Year: |
2020 |
| Construction Type: |
Street |
| District: |
|
|
PROJECT CONTACT: |
| Project Manager: |
Steve Sonntag |
| Phone: |
608-267-1997 |
| Email: |
ssonntag@cityofmadison.com |
| Inspector: |
Not Available |
| Phone: |
Not Available |