                | PUBLIC WORKS CONTRACTS
				
				
			
						
						
						
							| CONTRACT NUMBER: 8536 CONTRACT: McKenna Blvd Flood Mitigation - Phase 2 (Greentree Pond to N Struck St)
 Percentage of Contract Completed:
										98.49%
 |  
							| Associated Projects: 
									
										McKenna Blvd Flood Mitigation - Phase 2 (Greentree Pond to N Struck St) (12746) |  
						  
								
									 
									   | PROJECT: | McKenna Blvd Flood Mitigation - Phase 2 (Greentree Pond to N Struck St) |  
										| Project Number: | 12746 |  
										| Bid Due Date: | 04/09/20 |  
										| Bid Open Date: | 04/09/2020 |  
										| Estimated Start Date: | 06/17/2020 |  
										| Estimated Completion Date: | 08/11/2020 
 |  
										| Percent of Project Completed: | 98.49 % |  
										| Contract Amount: | $1,262,371.23 |  
										| Project Contractor: | SPEEDWAY SAND & GRAVEL INC |  
										| Construction Year: | 2020 |  
									  | Construction Type: | Storm |  
									  | District: | 19,
											20, |  
										| PROJECT CONTACT: |  
									   | Project Manager: | Matt Allie |  
									   | Phone: | 608 266-4058 |  
									   | Email: | mallie@cityofmadison.com |  
											| Inspector: | Mael, Stewart |  
											| Phone: | 261-9695 |  