CONTRACT NUMBER: 8561
CONTRACT: Hillcrest Dr, Alden Dr, Standish Ct Reconstruction
Percentage of Contract Completed:
91.56%
|
Associated Projects:
- Hillcrest Dr, Alden Dr, Standish Ct Reconstruction (12195)
|
PROJECT: |
Hillcrest Dr, Alden Dr, Standish Ct Reconstruction |
Project Number: |
12195 |
Bid Due Date: |
04/22/21
|
Bid Open Date: |
04/22/2021 |
Estimated Start Date: |
07/14/2021
|
Estimated Completion Date: |
10/01/2021
|
Percent of Project Completed: |
91.56 %
|
Contract Amount: |
$1,753,796.22
|
Project Contractor: |
S & L Underground, Inc.
|
Construction Year: |
2021 |
Construction Type: |
Street |
District: |
05,
11,
|
PROJECT CONTACT: |
Project Manager: |
Andy Zwieg |
Phone: |
608-266-9219 |
Email: |
azwieg@cityofmadison.com |
Inspector: |
Armstrong, Steve |
Phone: |
266-4914 |