PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 8570
CONTRACT: Local Road Traffic Calming & Arterial Ped Enhancements 2021
Percentage of Contract Completed:
94.05%
|
Associated Projects:
- Local Road Traffic Calming & Arterial Ped Enhancements 2021 (13264)
|
PROJECT: |
Local Road Traffic Calming & Arterial Ped Enhancements 2021 |
Project Number: |
13264 |
Bid Due Date: |
06/24/21
|
Bid Open Date: |
06/24/2021 |
Estimated Start Date: |
08/16/2021
|
Estimated Completion Date: |
11/20/2021
|
Percent of Project Completed: |
94.05 %
|
Contract Amount: |
$337,749.05
|
Project Contractor: |
Parisi Construction Co., Inc.
|
Construction Year: |
2021 |
Construction Type: |
Street |
District: |
|
PROJECT CONTACT: |
Project Manager: |
Jim Wolfe |
Phone: |
608-266-4099 |
Email: |
jwolfe@cityofmadison.com |
Inspector: |
Armstrong, Steve |
Phone: |
266-4914 |