PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 8584
CONTRACT: N. Park Street Paver Repair & State Street Sidewalk Joint Repair
Percentage of Contract Completed:
98.99%
|
Associated Projects:
- N. Park Street Paver Repair & State Street Sidewalk Joint Repair (13324)
|
| PROJECT: |
N. Park Street Paver Repair & State Street Sidewalk Joint Repair |
| Project Number: |
13324 |
| Bid Due Date: |
05/27/21
|
| Bid Open Date: |
05/27/2021 |
| Estimated Start Date: |
07/19/2021
|
| Estimated Completion Date: |
08/27/2021
|
| Percent of Project Completed: |
98.99 %
|
| Contract Amount: |
$399,876.54
|
| Project Contractor: |
SPEEDWAY SAND & GRAVEL INC
|
| Construction Year: |
2021 |
| Construction Type: |
Sidewalk |
| District: |
02,
04,
08,
|
|
PROJECT CONTACT: |
| Project Manager: |
Fadi El Musa Gonzalez |
| Phone: |
608-243-5214 |
| Email: |
felmusagonzalez@cityofmadison.com |
| Inspector: |
Hoel, Eric |
| Phone: |
|
Documents & Specs
|