PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 8622
CONTRACT: S. Owen, Caromar, Keating Resurfacing w/Utilities
Percentage of Contract Completed:
92.77%
|
Associated Projects:
- S. Owen, Caromar, Keating Resurfacing w/Utilities (13706)
|
PROJECT: |
S. Owen, Caromar, Keating Resurfacing w/Utilities |
Project Number: |
13706 |
Bid Due Date: |
03/24/22
|
Bid Open Date: |
03/24/2022 |
Estimated Start Date: |
06/16/2022
|
Estimated Completion Date: |
08/29/2022
|
Percent of Project Completed: |
92.77 %
|
Contract Amount: |
$1,818,181.81
|
Project Contractor: |
Parisi Construction LLC
|
Construction Year: |
2022 |
Construction Type: |
Street |
District: |
11,
|
PROJECT CONTACT: |
Project Manager: |
Steve Sonntag |
Phone: |
608-267-1997 |
Email: |
ssonntag@cityofmadison.com |
Inspector: |
Armstrong, Steve |
Phone: |
266-4914 |
Documents & Specs
|