PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 8634
CONTRACT: Sidewalk, Curb&Gutter, Citywide Installation and Repair 2022
Percentage of Contract Completed:
98.78%
|
Associated Projects:
- Sidewalk, Curb&Gutter, Citywide Installation and Repair 2022 (13721)
|
PROJECT: |
Sidewalk, Curb&Gutter, Citywide Installation and Repair 2022 |
Project Number: |
13721 |
Bid Due Date: |
04/07/22
|
Bid Open Date: |
04/07/2022 |
Estimated Start Date: |
06/06/2022
|
Estimated Completion Date: |
Not Available
|
Percent of Project Completed: |
98.78 %
|
Contract Amount: |
$481,890.00
|
Project Contractor: |
Raymond P. Cattell Inc.
|
Construction Year: |
2022 |
Construction Type: |
Sidewalk |
District: |
|
PROJECT CONTACT: |
Project Manager: |
Bill McGlynn |
Phone: |
608- 266-4537 |
Email: |
wmcglynn@cityofmadison.com |
Inspector: |
Not Available |
Phone: |
Not Available |
Documents & Specs
|