							| CONTRACT NUMBER: 8641 CONTRACT: Braxton Pl Resurfacing & La Mariposa Lane(new street)
 Percentage of Contract Completed:
										86.16%
 |  
							| Associated Projects: 
									
										Braxton Pl Resurfacing & La Mariposa Lane(new street) (13169) |  
						  
								
									 
									   | PROJECT: | Braxton Pl Resurfacing & La Mariposa Lane(new street) |  
										| Project Number: | 13169 |  
										| Bid Due Date: | 01/26/23 |  
										| Bid Open Date: | 01/26/2023 |  
										| Estimated Start Date: | 03/23/2023 |  
										| Estimated Completion Date: | 08/25/2023 
 |  
										| Percent of Project Completed: | 86.16 % |  
										| Contract Amount: | $1,141,497.82 |  
										| Project Contractor: | Capitol Underground |  
										| Construction Year: | 2023 |  
									  | Construction Type: | Street |  
									  | District: | 13, |  
										| PROJECT CONTACT: |  
									   | Project Manager: | Andy Zwieg |  
									   | Phone: | 608-266-9219 |  
									   | Email: | azwieg@cityofmadison.com |  
											| Inspector: | Hoel, Eric |  
											| Phone: |  |  