PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 8650
CONTRACT: Old Middleton Rd & Craig Ave Resurfacing w/Utilties
Percentage of Contract Completed:
96.96%
|
Associated Projects:
- Old Middleton Rd & Craig Ave Resurfacing w/Utilties (13175)
|
| PROJECT: |
Old Middleton Rd & Craig Ave Resurfacing w/Utilties |
| Project Number: |
13175 |
| Bid Due Date: |
03/17/22
|
| Bid Open Date: |
03/17/2022 |
| Estimated Start Date: |
04/18/2022
|
| Estimated Completion Date: |
08/01/2023
|
| Percent of Project Completed: |
96.96 %
|
| Contract Amount: |
$7,275,045.47
|
| Project Contractor: |
SPEEDWAY SAND & GRAVEL INC
|
| Construction Year: |
2023 |
| Construction Type: |
Street |
| District: |
11,
19,
|
|
PROJECT CONTACT: |
| Project Manager: |
Fadi El Musa Gonzalez |
| Phone: |
608-243-5214 |
| Email: |
felmusagonzalez@cityofmadison.com |
| Inspector: |
Armstrong, Steve |
| Phone: |
266-4914 |