PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 8688
CONTRACT: Chip Seal East
Percentage of Contract Completed:
99.26%
|
Associated Projects:
- Pavement Crack Repair and Chip Seal 2022 (13719)
|
| PROJECT: |
Pavement Crack Repair and Chip Seal 2022 |
| Project Number: |
13719 |
| Bid Due Date: |
04/07/22
|
| Bid Open Date: |
04/07/2022 |
| Estimated Start Date: |
06/06/2022
|
| Estimated Completion Date: |
Not Available
|
| Percent of Project Completed: |
99.26 %
|
| Contract Amount: |
$1,864,342.00
|
| Project Contractor: |
SCOTT CONSTRUCTION INC
|
| Construction Year: |
2022 |
| Construction Type: |
Street |
| District: |
|
|
PROJECT CONTACT: |
| Project Manager: |
Steve Sonntag |
| Phone: |
608-267-1997 |
| Email: |
ssonntag@cityofmadison.com |
| Inspector: |
Not Available |
| Phone: |
Not Available |