CONTRACT NUMBER: 8693
CONTRACT: Sheboygan Ave & N. Segoe Rd Resurfacing w/Utilities
Percentage of Contract Completed:
88.34%
|
Associated Projects:
- Sheboygan Ave & N. Segoe Rd Resurfacing w/Utilities (14215)
|
PROJECT: |
Sheboygan Ave & N. Segoe Rd Resurfacing w/Utilities |
Project Number: |
14215 |
Bid Due Date: |
12/14/23
|
Bid Open Date: |
12/14/2023 |
Estimated Start Date: |
03/20/2024
|
Estimated Completion Date: |
07/18/2024
|
Percent of Project Completed: |
88.34 %
|
Contract Amount: |
$4,410,674.23
|
Project Contractor: |
S & L Underground, Inc.
|
Construction Year: |
2023 |
Construction Type: |
Street |
District: |
11,
|
PROJECT CONTACT: |
Project Manager: |
Mario Galindez |
Phone: |
266-4095 |
Email: |
mgalindez@cityofmadison.com |
Inspector: |
Belohlavek, Rachel |
Phone: |
608-7836 |