PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 8706
CONTRACT: Sidewalk Ordered 2023 AD 18
Percentage of Contract Completed:
92.13%
|
Associated Projects:
- Sidewalk Ordered 2023 AD 18 (14349)
|
PROJECT: |
Sidewalk Ordered 2023 AD 18 |
Project Number: |
14349 |
Bid Due Date: |
02/23/23
|
Bid Open Date: |
02/23/2023 |
Estimated Start Date: |
04/17/2023
|
Estimated Completion Date: |
Not Available
|
Percent of Project Completed: |
92.13 %
|
Contract Amount: |
$1,817,462.90
|
Project Contractor: |
SPEEDWAY SAND & GRAVEL INC
|
Construction Year: |
2023 |
Construction Type: |
Sidewalk |
District: |
18,
|
PROJECT CONTACT: |
Project Manager: |
Bill McGlynn |
Phone: |
608- 266-4537 |
Email: |
wmcglynn@cityofmadison.com |
Inspector: |
Not Available |
Phone: |
Not Available |