PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 8711
CONTRACT: Harvey St & Schmitt Pl Reconstruction
Percentage of Contract Completed:
89.24%
|
Associated Projects:
- Harvey St & Schmitt Pl Reconstruction (14081)
|
| PROJECT: |
Harvey St & Schmitt Pl Reconstruction |
| Project Number: |
14081 |
| Bid Due Date: |
11/30/23
|
| Bid Open Date: |
11/30/2023 |
| Estimated Start Date: |
03/25/2024
|
| Estimated Completion Date: |
07/26/2024
|
| Percent of Project Completed: |
89.24 %
|
| Contract Amount: |
$1,056,614.70
|
| Project Contractor: |
S & L Underground, Inc.
|
| Construction Year: |
2024 |
| Construction Type: |
Street |
| District: |
05,
|
|
PROJECT CONTACT: |
| Project Manager: |
Steve Sonntag |
| Phone: |
608-267-1997 |
| Email: |
ssonntag@cityofmadison.com |
| Inspector: |
Belohlavek, Rachel |
| Phone: |
608-7836 |
Documents & Specs
|