PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 8711
CONTRACT: Harvey St & Schmitt Pl Reconstruction
Percentage of Contract Completed:
87.33%
|
Associated Projects:
- Harvey St & Schmitt Pl Reconstruction (14081)
|
PROJECT: |
Harvey St & Schmitt Pl Reconstruction |
Project Number: |
14081 |
Bid Due Date: |
11/30/23
|
Bid Open Date: |
11/30/2023 |
Estimated Start Date: |
03/25/2024
|
Estimated Completion Date: |
07/26/2024
|
Percent of Project Completed: |
87.33 %
|
Contract Amount: |
$1,056,614.70
|
Project Contractor: |
S & L Underground, Inc.
|
Construction Year: |
2024 |
Construction Type: |
Street |
District: |
05,
|
PROJECT CONTACT: |
Project Manager: |
Steve Sonntag |
Phone: |
608-267-1997 |
Email: |
ssonntag@cityofmadison.com |
Inspector: |
Belohlavek, Rachel |
Phone: |
608-7836 |
Documents & Specs
|