CONTRACT NUMBER: 8745
CONTRACT: Stevens Resurfacing w/utilities
Percentage of Contract Completed:
94.09%
|
Associated Projects:
- Stevens St Resurfacing w/ Utilities (14764)
|
| PROJECT: |
Stevens St Resurfacing w/ Utilities |
| Project Number: |
14764 |
| Bid Due Date: |
05/23/24
|
| Bid Open Date: |
05/23/2024 |
| Estimated Start Date: |
08/05/2024
|
| Estimated Completion Date: |
11/01/2024
|
| Percent of Project Completed: |
94.09 %
|
| Contract Amount: |
$1,364,036.01
|
| Project Contractor: |
Capitol Underground
|
| Construction Year: |
2024 |
| Construction Type: |
Street |
| District: |
05,
|
|
PROJECT CONTACT: |
| Project Manager: |
Grecia Izquierdo |
| Phone: |
|
| Email: |
gizquierdo@cityofmadison.com |
| Inspector: |
Belohlavek, Rachel |
| Phone: |
608-7836 |