CONTRACT NUMBER: 8762
CONTRACT: Hammersley Road Resurfacing w/Utilities Phase 2
Percentage of Contract Completed:
92.51%
|
Associated Projects:
- Hammersley Road Resurfacing w/Utilities Phase 2 (13924)
|
| PROJECT: |
Hammersley Road Resurfacing w/Utilities Phase 2 |
| Project Number: |
13924 |
| Bid Due Date: |
11/30/23
|
| Bid Open Date: |
11/30/2023 |
| Estimated Start Date: |
02/12/2024
|
| Estimated Completion Date: |
Not Available
|
| Percent of Project Completed: |
92.51 %
|
| Contract Amount: |
$4,469,002.93
|
| Project Contractor: |
Capitol Underground
|
| Construction Year: |
2024 |
| Construction Type: |
Street |
| District: |
10,
|
|
PROJECT CONTACT: |
| Project Manager: |
Aaron Canton |
| Phone: |
(608) 242-4763 |
| Email: |
acanton@cityofmadison.com |
| Inspector: |
Voeck, Jim |
| Phone: |
608520-2600 |