PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 8770
CONTRACT: West Towne Path Ph 2a
Percentage of Contract Completed:
37.28%
|
Associated Projects:
- West Towne Path Ph 2a (10169)
|
| PROJECT: |
West Towne Path Ph 2a |
| Project Number: |
10169 |
| Bid Due Date: |
09/26/24
|
| Bid Open Date: |
09/26/2024 |
| Estimated Start Date: |
05/05/2025
|
| Estimated Completion Date: |
07/01/2025
|
| Percent of Project Completed: |
37.28 %
|
| Contract Amount: |
$719,999.99
|
| Project Contractor: |
Parisi Construction LLC
|
| Construction Year: |
2025 |
| Construction Type: |
|
| District: |
09,
|
|
PROJECT CONTACT: |
| Project Manager: |
Aaron Canton |
| Phone: |
(608) 242-4763 |
| Email: |
acanton@cityofmadison.com |
| Inspector: |
Gottschalk, Jim |
| Phone: |
608-535-7819 |
Documents & Specs
|