CONTRACT NUMBER: 8781
CONTRACT: Evergreen Ave, Ohio Ave, and Sommers Ave Recon
Percentage of Contract Completed: 8.74%
Associated Projects:
  • Evergreen Ave, Ohio Ave, Sommers Ave Recon (11825)
PROJECT: Evergreen Ave, Ohio Ave, Sommers Ave Recon
Project Number: 11825
Bid Due Date: 03/27/25
Bid Open Date: 03/27/2025
Estimated Start Date: 06/09/2025
Estimated Completion Date: 11/01/2025
Percent of Project Completed: 8.74 %
Contract Amount: $2,723,321.88
Project Contractor: SPEEDWAY SAND & GRAVEL INC
Construction Year: 2025
Construction Type: Street
District: 15,
PROJECT CONTACT:
Project Manager: Andy Zwieg
Phone: 608-266-9219
Email: azwieg@cityofmadison.com
Inspector: Lauby, Paul
Phone: 520-2378