PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 8791
CONTRACT: Sawcutting Dist 20
Percentage of Contract Completed:
7.21%
|
Associated Projects:
- Sawcutting Dist 10 & 20 (15378)
|
| PROJECT: |
Sawcutting Dist 10 & 20 |
| Project Number: |
15378 |
| Bid Due Date: |
02/27/25
|
| Bid Open Date: |
02/27/2025 |
| Estimated Start Date: |
05/05/2025
|
| Estimated Completion Date: |
Not Available
|
| Percent of Project Completed: |
7.21 %
|
| Contract Amount: |
$142,755.00
|
| Project Contractor: |
Madison Commercial Landscpaes, Inc
|
| Construction Year: |
2025 |
| Construction Type: |
Sidewalk |
| District: |
10,
|
|
PROJECT CONTACT: |
| Project Manager: |
Bill McGlynn |
| Phone: |
608- 266-4537 |
| Email: |
wmcglynn@cityofmadison.com |
| Inspector: |
Not Available |
| Phone: |
Not Available |
Documents & Specs
|