PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 8800
CONTRACT: 2025 Safe Streets
Percentage of Contract Completed:
Not Available
|
Associated Projects:
- 2025 Safe Streets (15200)
|
PROJECT: |
2025 Safe Streets |
Project Number: |
15200 |
Bid Due Date: |
03/20/25
|
Bid Open Date: |
03/20/2025 |
Estimated Start Date: |
05/19/2025
|
Estimated Completion Date: |
Not Available
|
Percent of Project Completed: |
Not Available
|
Contract Amount: |
$2,045,968.40
|
Project Contractor: |
Parisi Construction LLC
|
Construction Year: |
2025 |
Construction Type: |
Sidewalk |
District: |
|
PROJECT CONTACT: |
Project Manager: |
Mario Galindez |
Phone: |
266-4095 |
Email: |
mgalindez@cityofmadison.com |
Inspector: |
Not Available |
Phone: |
Not Available |
Documents & Specs
|