CONTRACT NUMBER: 8806
CONTRACT: Buffalo Trail, Barron Court, Green Lake Pass Resurfacing w/Utilities
Percentage of Contract Completed: 32.67%
Associated Projects:
  • Buffalo Trail, Barron Court, Green Lake Pass Resurfacing w/Utilities (15123)
PROJECT: Buffalo Trail, Barron Court, Green Lake Pass Resurfacing w/Utilities
Project Number: 15123
Bid Due Date: 08/07/25
Bid Open Date: 08/07/2025
Estimated Start Date: 04/06/2026
Estimated Completion Date: 07/03/2026
Percent of Project Completed: 32.67 %
Contract Amount: Not Available
Project Contractor:
Construction Year: 2025
Construction Type: Street
District: 11,
PROJECT CONTACT:
Project Manager: Andy Zwieg
Phone: 608-266-9219
Email: azwieg@cityofmadison.com
Inspector: Gottschalk, Jim
Phone: 608-535-7819