PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 8853
CONTRACT: Park Paving 2020
Percentage of Contract Completed:
Not Available
|
|
Associated Projects:
|
| PROJECT: |
Park Paving 2020 |
| Project Number: |
12827 |
| Bid Due Date: |
04/09/20
|
| Bid Open Date: |
04/09/2020 |
| Estimated Start Date: |
06/01/2020
|
| Estimated Completion Date: |
Not Available
|
| Percent of Project Completed: |
Not Available
|
| Contract Amount: |
$376,947.48
|
| Project Contractor: |
Joe Daniels Construction Co., Inc.
|
| Construction Year: |
|
| Construction Type: |
|
| District: |
03,
06,
09,
10,
11,
17,
18,
20,
|
|
PROJECT CONTACT: |
| Project Manager: |
Corey Stelljes |
| Phone: |
608-266-6518 |
| Email: |
cstelljes@cityofmadison.com |
| Inspector: |
Not Available |
| Phone: |
Not Available |