PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 8864
CONTRACT: E. Gorham Street Assessment District - 2020
Percentage of Contract Completed:
93.11%
|
Associated Projects:
- E. Gorham Street Resurfacing: Utilities (12989)
|
| PROJECT: |
E. Gorham Street Resurfacing: Utilities |
| Project Number: |
12989 |
| Bid Due Date: |
05/28/20
|
| Bid Open Date: |
05/28/2020 |
| Estimated Start Date: |
08/10/2020
|
| Estimated Completion Date: |
10/23/2020
|
| Percent of Project Completed: |
93.11 %
|
| Contract Amount: |
$1,771,601.23
|
| Project Contractor: |
SPEEDWAY SAND & GRAVEL INC
|
| Construction Year: |
2020 |
| Construction Type: |
Street |
| District: |
02,
|
|
PROJECT CONTACT: |
| Project Manager: |
Kyle Frank |
| Phone: |
608-266-4098 |
| Email: |
kfrank@cityofmadison.com |
| Inspector: |
Lauby, Paul |
| Phone: |
520-2378 |
Documents & Specs
|