PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 8875
CONTRACT: Lower Badger Mill Creek Pond at Hill Creek Park
Percentage of Contract Completed:
88.86%
|
Associated Projects:
- Lower Badger Mill Creek Pond (11063)
|
| PROJECT: |
Lower Badger Mill Creek Pond |
| Project Number: |
11063 |
| Bid Due Date: |
03/09/23
|
| Bid Open Date: |
03/09/2023 |
| Estimated Start Date: |
05/08/2023
|
| Estimated Completion Date: |
10/27/2023
|
| Percent of Project Completed: |
88.86 %
|
| Contract Amount: |
$2,664,573.72
|
| Project Contractor: |
Integrity Grading and Excavating, Inc.
|
| Construction Year: |
2023 |
| Construction Type: |
Storm |
| District: |
01,
|
|
PROJECT CONTACT: |
| Project Manager: |
Sarah Lerner |
| Phone: |
608-261-8592 |
| Email: |
slerner@cityofmadison.com |
| Inspector: |
Belohlavek, Rachel |
| Phone: |
608-7836 |
Documents & Specs
|