PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 9063
CONTRACT: Thurber Lift Station Replacement
Percentage of Contract Completed:
99.88%
|
Associated Projects:
- Thurber Lift Station Replacement (11672)
|
PROJECT: |
Thurber Lift Station Replacement |
Project Number: |
11672 |
Bid Due Date: |
09/23/21
|
Bid Open Date: |
09/23/2021 |
Estimated Start Date: |
10/10/2023
|
Estimated Completion Date: |
10/20/2022
|
Percent of Project Completed: |
99.88 %
|
Contract Amount: |
$987,654.32
|
Project Contractor: |
SPEEDWAY SAND & GRAVEL INC
|
Construction Year: |
2022 |
Construction Type: |
Sanitary |
District: |
06,
|
PROJECT CONTACT: |
Project Manager: |
Kyle Frank |
Phone: |
608-266-4098 |
Email: |
kfrank@cityofmadison.com |
Inspector: |
Lauby, Paul |
Phone: |
|
Documents & Specs
|