PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 9103
CONTRACT: Worthington Ave Sanitary Replacement
Percentage of Contract Completed:
95.60%
|
Associated Projects:
- Worthington Avenue Sanitary Replacement (13800)
|
PROJECT: |
Worthington Avenue Sanitary Replacement |
Project Number: |
13800 |
Bid Due Date: |
05/12/22
|
Bid Open Date: |
05/12/2022 |
Estimated Start Date: |
07/08/2022
|
Estimated Completion Date: |
09/20/2022
|
Percent of Project Completed: |
95.60 %
|
Contract Amount: |
$965,284.86
|
Project Contractor: |
Capitol Underground
|
Construction Year: |
2022 |
Construction Type: |
Sanitary |
District: |
|
PROJECT CONTACT: |
Project Manager: |
Kyle Frank |
Phone: |
608-266-4098 |
Email: |
kfrank@cityofmadison.com |
Inspector: |
Lauby, Paul |
Phone: |
|
Documents & Specs
|