CONTRACT NUMBER: 9319
CONTRACT: CIPP Water Main Rehab 2023 - Fish Hatchery Road & Lake Mendota Drive
Percentage of Contract Completed:
Not Available
|
Associated Projects:
- CIPP Water Main Rehab 2023 - Fish Hatchery Road (14643)
- CIPP Water Main Rehab 2023 - Lake Mendota Drive (14659)
|
PROJECT: |
CIPP Water Main Rehab 2023 - Fish Hatchery Road |
Project Number: |
14643 |
Bid Due Date: |
05/25/23
|
Bid Open Date: |
05/25/2023 |
Estimated Start Date: |
07/17/2023
|
Estimated Completion Date: |
Not Available
|
Percent of Project Completed: |
Not Available
|
Contract Amount: |
$749,880.00
|
Project Contractor: |
Fer-Pal Construction USA LLC
|
Construction Year: |
|
Construction Type: |
|
District: |
14,
19,
|
PROJECT CONTACT: |
Project Manager: |
Peter Holmgren |
Phone: |
261-5530 |
Email: |
pholmgren@madisonwater.org |
Inspector: |
Not Available |
Phone: |
Not Available |
PROJECT: |
CIPP Water Main Rehab 2023 - Lake Mendota Drive |
Project Number: |
14659 |
Bid Due Date: |
05/25/23
|
Bid Open Date: |
05/25/2023 |
Estimated Start Date: |
07/17/2023
|
Estimated Completion Date: |
Not Available
|
Percent of Project Completed: |
Not Available
|
Contract Amount: |
$749,880.00
|
Project Contractor: |
Fer-Pal Construction USA LLC
|
Construction Year: |
|
Construction Type: |
|
District: |
19,
|
PROJECT CONTACT: |
Project Manager: |
|
Phone: |
|
Email: |
|
Inspector: |
Not Available |
Phone: |
Not Available |
Documents & Specs
|