PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 9336
CONTRACT: 229 Felland Road Booster Pump Install
Percentage of Contract Completed:
Not Available
|
Associated Projects:
- 229 Felland Road Booster Pump Install (14413)
|
PROJECT: |
229 Felland Road Booster Pump Install |
Project Number: |
14413 |
Bid Due Date: |
09/21/23
|
Bid Open Date: |
09/21/2023 |
Estimated Start Date: |
Not Available
|
Estimated Completion Date: |
Not Available
|
Percent of Project Completed: |
Not Available
|
Contract Amount: |
$149,870.00
|
Project Contractor: |
Monona Plumbing & Fire Protection, Inc.
|
Construction Year: |
2023 |
Construction Type: |
|
District: |
03,
|
PROJECT CONTACT: |
Project Manager: |
Tim Pearson |
Phone: |
608 266-6215 |
Email: |
tpearson@madisonwater.org |
Inspector: |
Not Available |
Phone: |
Not Available |
Documents & Specs
|