CONTRACT NUMBER: 9365
CONTRACT: Railroad Arch Culvert Repair at Southwest Bike Path
Percentage of Contract Completed:
99.93%
|
Associated Projects:
- Railroad Arch Culvert Repair at Southwest Path (14369)
|
| PROJECT: |
Railroad Arch Culvert Repair at Southwest Path |
| Project Number: |
14369 |
| Bid Due Date: |
09/21/23
|
| Bid Open Date: |
09/21/2023 |
| Estimated Start Date: |
04/15/2024
|
| Estimated Completion Date: |
05/30/2024
|
| Percent of Project Completed: |
99.93 %
|
| Contract Amount: |
$215,789.25
|
| Project Contractor: |
SPEEDWAY SAND & GRAVEL INC
|
| Construction Year: |
2023 |
| Construction Type: |
Storm |
| District: |
13,
|
|
PROJECT CONTACT: |
| Project Manager: |
Sarah Lerner |
| Phone: |
608-261-8592 |
| Email: |
slerner@cityofmadison.com |
| Inspector: |
Beer, Shawn |
| Phone: |
608-219-8165 |