CONTRACT NUMBER: 9365
CONTRACT: Railroad Arch Culvert Repair at Southwest Bike Path
Percentage of Contract Completed:
99.93%
|
Associated Projects:
- Railroad Arch Culvert Repair at Southwest Path (14369)
|
PROJECT: |
Railroad Arch Culvert Repair at Southwest Path |
Project Number: |
14369 |
Bid Due Date: |
09/21/23
|
Bid Open Date: |
09/21/2023 |
Estimated Start Date: |
04/15/2024
|
Estimated Completion Date: |
05/30/2024
|
Percent of Project Completed: |
99.93 %
|
Contract Amount: |
$215,789.25
|
Project Contractor: |
SPEEDWAY SAND & GRAVEL INC
|