Skip to main content

City of Madison

Image: Public Works Header

PUBLIC WORKS CONTRACTS

CONTRACT NUMBER: 9377
CONTRACT: University Avenue Box Repair 2023
Percentage of Contract Completed: 91.50%
Associated Projects:
  • University Avenue Reconstruction (11168)
PROJECT: University Avenue Reconstruction
Project Number: 11168
Bid Due Date: 11/09/23
Bid Open Date: 11/09/2023
Estimated Start Date: 01/15/2024
Estimated Completion Date: 03/04/2024
Percent of Project Completed: 91.50 %
Contract Amount: $644,737.00
Project Contractor: SPEEDWAY SAND & GRAVEL INC
Construction Year: 2023
Construction Type: Street
District: 05,
PROJECT CONTACT:
Project Manager: Jim Wolfe
Phone: 608-266-4099
Email: jwolfe@cityofmadison.com
Inspector: Not Available
Phone: Not Available


Documents & Specs