PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 9426
CONTRACT: CIPP Rehab of Sanitary and Storm Sewer Mains - 2019
Percentage of Contract Completed:
99.99%
|
Associated Projects:
- CIPP Rehab of Sanitary and Storm Sewer Mains - 2019 (12710)
|
PROJECT: |
CIPP Rehab of Sanitary and Storm Sewer Mains - 2019 |
Project Number: |
12710 |
Bid Due Date: |
11/07/19
|
Bid Open Date: |
11/07/2019 |
Estimated Start Date: |
12/30/2019
|
Estimated Completion Date: |
Not Available
|
Percent of Project Completed: |
99.99 %
|
Contract Amount: |
$842,731.65
|
Project Contractor: |
VISU-SEWER, LLC
|
Construction Year: |
2020 |
Construction Type: |
Sanitary |
District: |
|
PROJECT CONTACT: |
Project Manager: |
Kyle Frank |
Phone: |
608-266-4098 |
Email: |
kfrank@cityofmadison.com |
Inspector: |
Not Available |
Phone: |
Not Available |