PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 9489
CONTRACT: 3400 BLK E Washington Sewer Replacement
Percentage of Contract Completed:
93.05%
|
Associated Projects:
- 3400 BLK E Washington Sewer Repl (14920)
|
PROJECT: |
3400 BLK E Washington Sewer Repl |
Project Number: |
14920 |
Bid Due Date: |
07/18/24
|
Bid Open Date: |
07/18/2024 |
Estimated Start Date: |
10/14/2024
|
Estimated Completion Date: |
11/01/2024
|
Percent of Project Completed: |
93.05 %
|
Contract Amount: |
$378,203.55
|
Project Contractor: |
SPEEDWAY SAND & GRAVEL INC
|
Construction Year: |
|
Construction Type: |
Sanitary |
District: |
|
PROJECT CONTACT: |
Project Manager: |
Daniel Olivares |
Phone: |
261-9285 |
Email: |
daolivares@cityofmadison.com |
Inspector: |
Lauby, Paul |
Phone: |
|
Documents & Specs
|